The Lismore Recycling & Recovery Centre (LRRC) will soon benefit from improved and safer access, smoother traffic flow and enhanced facilities, says Lismore City Council.
They say a major improvement program is set to begin next month.
Council say, ‘To be completed in stages between August 2026 to February 2027, the project includes a new western sediment basin to capture and temporarily store stormwater runoff, upgraded internal roads and dedicated heavy vehicle routes, better drainage, a new roundabout, and enhancements to the popular Revolve Shop’.
‘Roads impacted during the 2022 flood response will also be repaired.
‘As part of the program, LRRC’s popular Revolve Shop will temporarily close for approximately 10 weeks from October to facilitate parking and access improvements to the precinct.
‘These works are part of council’s broader commitment to preparing Lismore’s waste and resource recovery system for the future. As the community grows and expectations around recycling, reuse and sustainability continue to evolve, Council is investing in facilities that make it easier for residents to recover more valuable resources and send less residual waste to landfill.
‘The Revolve Shop diverts thousands of items from landfill each year and demonstrates how everyday items can be given a second life. It is one example of the important role resource recovery plays in Lismore’s future and remains a valued community destination for affordable, pre-loved goods.
‘Council understands the temporary closure may cause some inconvenience and thanks customers for their patience while work is underway’.
Lismore City Mayor Steve Krieg said the project supports Council’s long-term vision for waste management while delivering practical benefits for the community.
‘The LRRC is one of Council’s busiest community facilities, and these works will make it safer, easier to use and better equipped to serve the community for years to come,’ Mayor Krieg said.
‘These important improvements are about more than today’s customer experience. They’re part of how we are preparing Lismore for the future.’
‘Customers will benefit from better access, additional parking and improved traffic flow, while dedicated haul roads will separate heavy vehicles from public areas, creating a safer environment across the site.
Future waste planning a significant challenge
‘Across Australia we’re seeing future waste planning become a significant challenge for local governments. By investing now we’re making sure Lismore is ready for that future.
‘The broader LRRC will remain open throughout construction wherever possible. However, customers may encounter temporary traffic changes, altered access arrangements and short-term diversions as work progresses.
‘Council will provide advance notice of any significant impacts and keep the community informed through its website, social media channels and on-site signage.
‘These upgrades are jointly funded by the Australian and NSW Governments under the Disaster Recovery Funding Arrangements and Infrastructure Betterment programs.
‘To learn more about waste and recycling services and Council’s work to plan Lismore’s future resource recovery system, visit lismore.nsw.gov.au’