Flood damage repairs finally start in Tweed

Latest News

Vaccinations

Vyvyan Stott, Mullumbumby The government doctors have announced that vaccinations are compulsory for nurses . Yet our constitution states parliament may...

Other News

Two WRHS rescue flights from Tabulam in one day

The Westpac Rescue Helicopter Service (WRHS) say they travelled to Tabulam twice yesterday in separate incidents in the town.

Massive multi-dwelling Paterson Street DA before Planning Panel

The Northern Regional Planning Panel (NRPP), an unelected consent authority that overrides Council decision making, will be considering a...

Pro rail groups join to rally on Thursday

Four local groups have banded together and will host a rally calling for urgent consultation on the removal of the train tracks on the Murwillumbah to Crabbes Creek rail corridor.

Calls for Minister to conduct ‘genuine’ consultation on Murwillumbah mega-school

The Murwillumbah community and SOS (Save Our Schools) are calling on the NSW Minister for Education, Sarah Mitchell to...

‘Influencers’ – just another advertising platform…

The question being asked by many consumers is 'are influencers genuinely promoting products that they like and believe in, or is it just more advertising?

You Can Close Your Eyes

There is a beautiful James Taylor song (‘You Can Close Your Eyes’) that commences with the words; Oh, the sun is surely sinking down, But the moon is slowly rising. 

Work is finally about to start on road and bridges damaged during the March 31 floods in Tweed Shire. Photo Tweed Shire Council
Work is finally about to start on road and bridges damaged during the March 31 floods in Tweed Shire. Photo Tweed Shire Council

Tweed Shire Council has awarded a large package of flood remediation works in its first round of minor to medium-sized jobs to restore roads and bridges damaged in the 31 March flood.

The tender has gone to contractor Queensland-based contractors G & R Brown & Sons Pty Ltd.

A council spokesperson says that three more packages will be released to a preferred panel of six contracting companies for quoting and be awarded over the next three to four months.

It could then take between six and nine months for the contractors to complete works, weather and site conditions permitting.

Council has bundled the jobs in geographic areas ‘to minimise travel times between jobs and maximise on-the-ground efficiencies,’ the spokesperson said.

The first package centres on Carool, Crystal Creek and Upper Crystal Creek, Bilambil, Dulguigan, Dungay, Duroby and Upper Duroby, Glengarrie, Nobbys Creek, Tomewin, Tumbulgum and North Tumbulgum.

It involves work to rectify more than 100 damaged items and is worth about $1.5 million.

Meanwhile, more than 50 major reconstruction jobs are in various stages of investigation and design.

The council says it is ‘is engaging extra contractor resources to get these jobs shovel-ready. Still, these jobs, which account for the bulk of the repair bill at about $16 million, are not expected to start before the end of the year and will take more than two years to complete.’

Flood restoration coordinator Nigel Dobson said that while it has taken six months to get to this point, ‘with a preferred contractor panel in place and work bundled into packages, residents should see a lot more activity shortly and the speed of road and bridge repairs will ramp up’.

The council estimates the flood caused approximately $27 million of damage to roads and bridges, of which 900 minor road and bridge damaged items have been repaired at a cost of $5.2 million.

It expects to recover $18.3 million of its roads bill through Natural Disaster Relief and Recovery Assistance (NDRRA) and grant funding, leaving a possible shortfall of $8.7 million to be funded from the council’s future operating and capital budgets.

‘These figures may change as we firm up damage estimates, work to maximise funding opportunities and when NDRRA assessments are completed,’ Mr Dobson said.

‘The federal government’s Bridge Renewal Program has granted $2.17 million in funds (50 per cent) towards the replacement of Byrrill Creek Bridge and the council is negotiating with Roads and Maritime Services as to whether disaster relief funding can be used for some of the remaining budget shortfall to get that project happening.’

‘NDRRA has strict funding rules, including that costs are recoverable only where the council uses contractor resources. That is, the council cannot use its own workforce to repair flood damage,’ he said.


Support The Echo

Keeping the community together and the community voice loud and clear is what The Echo is about. More than ever we need your help to keep this voice alive and thriving in the community.

Like all businesses we are struggling to keep food on the table of all our local and hard working journalists, artists, sales, delivery and drudges who keep the news coming out to you both in the newspaper and online. If you can spare a few dollars a week – or maybe more – we would appreciate all the support you are able to give to keep the voice of independent, local journalism alive.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Bad news

Raphael Lee Cass, Byron Bay I’ve taken umbrage with the expression, ‘fake news,’ – proud of our Echo – but the article on page 5,...

Tender to build rail trail from M’bah to Crabbes Creek awarded

The debate over the tender for the building of the rail trail between Murwillumbh and Crabbes Creek was ultimately held behind closed doors, Mayor...

Massive multi-dwelling Paterson Street DA before Planning Panel

The Northern Regional Planning Panel (NRPP), an unelected consent authority that overrides Council decision making, will be considering a 14 townhouse DA for Paterson...

Backsliders coming to Lennox

Australian music legends the Backsliders are coming to Lennox Head for the first time, to play at the Lennox Head Cultural Centre on Saturday 26 June 2021.